The Gjøa platform takes shape

12/01/2010 // In the days between Christmas and New Year, Aker Solutions successfully carried out a major marine operation on the Gjøa platform, under construction by Aker Solutions, as the deck and hull of the platform were mated together outside the yard at Stord. “I am impressed by this operation,” said Kjetel Rokseth Digre, Statoil’s project manager.

Gjøa is the largest ongoing field development project in the North Sea. Aker Solutions has carried out front end engineering design, detail design of topside and hull, procurement, construction and hook-up of topside, and mating of topside and hull. The company is also responsible for installation of the mooring system, transportation and installation of the semi-submersible production platform.

The dimensions of the Gjøa platform are huge. The deck (topside) weighs in at more than 20,000 tonnes, and the hull at around 15,000 tonnes. At the same time, the margin of error is small. With only a tolerance of 25 millimetres (1 inch) in all directions, the hull fit to the deck, which is about the size of a football field.

“This operation was well-planned, safe and efficient and carried out with the utmost precision,” said Rokseth Digre.More than 2,000 people from Aker Solutions and its suppliers have been working on Gjøa in recent months. Work will continue in the next months, in order to get the platform ready for tow-out and operations.Statoil is Gjøa’s development operator, while GDF Suez will take over as operator at production start-up. Other partners in the field are Petoro, Shell and RWE Dea.

During the last few days the deck and hull of the Gjøa platform have been mated together in the fjord outside the Norwegian town of Stord. There were exacting requirements for precision and weather conditions during the operation, which was a success.
 
Four guide pins had to meet their respective slots with a tolerance of just 25 millimetres (1 inch) in all directions. The operation was carried out by Aker Stord.The four-legged hull rose from the sea in the sea off Stord and ‘spiked’ the deck of the new North Sea giant, Gjøa. Four guide pins had to meet their respective slots in a deck the size of a football field, with a tolerance of just 25 millimetres (1 inch) in all directions. The guide pins are designed to take the load should the platform list, so that it can be towed to shore before the deck is welded to the hull, allowing mechanical testing and commissioning of the platform to start sooner.
 
Carried by special barge During the night, the ballast tanks in the hull were filled with water in order to submerge the structure to a depth of 35 metres. Only five metres of the hull protruded from the water when the barge carrying the platform deck was towed from the quay. The barge carrying the platform deck was manoeuvred into place between the columns of the hull.
Lifting the deck Slowly but surely, the ballast water was discharged; the hull rose towards the deck and they were mated into one.

When the operation was completed, the draught of the hull was 13 metres. The mated platform was then towed to the quay, so that the work of mechanical completion could continue. Planning saved time “I am impressed by this operation. It was well-planned, safe and efficient and carried out with the utmost precision,” says Kjetel Rokseth Digre, project manager for Gjøa. The mating was carried out by Aker Stord, who are constructing the platform for Statoil.
 
During the past couple of months, more than 2,000 people have worked continuous shifts on Gjøa in order to make it ready for towing to the field in April. By carrying out the mating between Christmas and New Year when most workers are on vacation, a large number of inoperative staff onshore has been avoided.

Building for a new operator “It was extremely important for us to get this done now. We now have a complete platform structure to work on, and we are doing everything in our power to get Gjøa ready by the agreed date,” says Digre. Statoil is operator during the development phase of the Gjøa field. The plan is for the platform and the field to be handed over in October 2010, to GDF Suez E&P Norge AS, who will be operator during the production phase. Gjøa will be GDF Suez’s first operatorship for a field in operation.


Share on your network   |   print